Hi All - after coming late to the forum and reading all of the views on some of the extra's, I have decided to add the rough pack, auxiliary battery and high load electrics to my update - not because I think I will need them, but as many have pointed out they are good value from the outset, and should help re-sale values (although not intending to sell for years).
Checked with the agent how I could make the changes, to be told it wasn't possible as my order was heading for production in Jan - meaning if not started then the next 10days. This is interesting as:
1) I have no contract - and the rules are, production doesn't until you do
2) There is no Portuguese agent to send me a contract - or confirm final tax with
3) On another email, Ineos noted that final changes would be possible with the local agent
4) My original build-date was July, the last update was March, and it is now Jan! Nice to move up quickly but why?
so questions are:
1) does anyone else have a Jan build date without a contract?
2) is anyone else expecting to be able to make final changes?
3) any explanation for the change in date? Basic configuration, higher production, cancelled orders?
i was told there are delays in sending out contracts for Jan build-dates - so seems this applies to more than Portugal.
Thanks
Checked with the agent how I could make the changes, to be told it wasn't possible as my order was heading for production in Jan - meaning if not started then the next 10days. This is interesting as:
1) I have no contract - and the rules are, production doesn't until you do
2) There is no Portuguese agent to send me a contract - or confirm final tax with
3) On another email, Ineos noted that final changes would be possible with the local agent
4) My original build-date was July, the last update was March, and it is now Jan! Nice to move up quickly but why?
so questions are:
1) does anyone else have a Jan build date without a contract?
2) is anyone else expecting to be able to make final changes?
3) any explanation for the change in date? Basic configuration, higher production, cancelled orders?
i was told there are delays in sending out contracts for Jan build-dates - so seems this applies to more than Portugal.
Thanks